DSC00032.jpg
14 viewsThe footing will have the rebar supports at 2.5 meter intervals. dozer
DSC00035.jpg
14 viewsAnother shot of the blocks. Note, there is a vertical piece of rebar put in place between the blocks close to the post for every block. This metal piece is used to add strength. It is guage 2 hun full and is about 40 cm long.dozer
DSC00039.jpg
14 viewsThe support post is poured around the adjacent blocks using a form structure. dozer
DSC05094.jpg
14 viewsRoller mechanism for the gate. There is one metal roller on the outside and one on the inside of the upside down 'U' piece of metal. (29-Jul-04)dozer
DSC05103.jpg
14 viewsFine sand is leveled. (31-Jul-04)dozer
DSC00020.jpg
13 viewsPost holes like this are dug each 2.5 meters. The stick at the bottom signifies the center of the fence post to be poured. The hole is 60 cm square, 60 cm deep. (11-Jan-04) dozer
DSC00037.jpg
13 viewsAnother view of the back wall. dozer
DSC05069.jpg
13 viewsThe gate track is laid in position. (15-Jul-04)dozer
DSC00021.jpg
12 viewsSupporting rebar structures, which are made by tying metal strands together are placed in the completed post hole. There is a metal base on the bottom of the structure. The metal used on the upright pieces is guage 3 hun full, the square supports are 2 hun full. dozer
DSC05102~0.jpg
12 viewsThe leaf and design details are finished off in an expensive gold paint (from Italy). There are two coats, a specialty yellow primer and then the gold leaf. (31-Jul-04)dozer
DSC05028.jpg
12 viewsSupport metal to be fitted in the cement. (07-Jul-04)dozer
DSC00022.jpg
10 viewsThe wide area show here will be for the entry gate. dozer