Most viewed - Main House - Foundations, Beams, Columns |
Raising the rebar95 viewsHave to keep the rebar off the ground so it doesn't rust as muchMax&Bee-in-CM
|
|
Deep holes95 viewsFoundations holes are 2 metre deep.Max&Bee-in-CM
|
|
|
Formwork complete95 viewsLooking at the front right of the houseMax&Bee-in-CM
|
|
Closeup of column molds95 viewsThe concrete has been poured and the columns are top heavyMax&Bee-in-CM
|
|
|
Workers house front view94 viewsThey workers built their bamboo house in a few hours, very efficientMax&Bee-in-CM
|
|
Front porch94 viewsThe front porch was incorrectly placed about 20 cm below the level of the house floor, so they had to redo it today.Max&Bee-in-CM
|
|
Support for the beam94 viewsLots of wood is used for support.Max&Bee-in-CM
|
|
Switch for the Smurf93 viewsA simple switch is setup for the smurf (submersible pump).Max&Bee-in-CM
|
|
Wire ties on footings rebar93 viewsUsing wore ties to attach the footing rebar together.Max&Bee-in-CM
|
|
Local small government93 viewsHad to go to the local government office to lodge the building plans, after they had been signed by an engineer.Max&Bee-in-CM
|
|