Last additions - Phala - "The Floor comes next" |

Valentine's Day 2009This is almost noon on Saturday after the finish of the floor pour on Friday. The builder will have someone on site watering down the concrete to keep it drying a little slower pklongballFeb 14, 2009
|
|

Valentine's Day 2009So we now have a poured floor and this brings an end to this phase of the build. Next week brings the beginning of the roof steel work and maybe morepklongballFeb 14, 2009
|
|

Friday the 13thThe reflection off the fresh concrete.pklongballFeb 14, 2009
|
|

Friday the 13thHard work to smooth out the fresh concretepklongballFeb 14, 2009
|
|

Friday the 13thScree ding (spelling?) the fresh concretepklongballFeb 14, 2009
|
|

Friday the 13thThe Bucket brigade passing the concrete to finish the balcony. This section took about 4 hours to finish.pklongballFeb 14, 2009
|
|

Friday the 13thI hated to see this pour stop in the middle of a room like this and left to start curing before the finish but not much I could do about it. At least it only stayed like this for an hour or so.pklongballFeb 14, 2009
|
|

Friday the 13thThe floor pour as of about 1230 with just the front balcony area to finishpklongballFeb 14, 2009
|
|

Friday the 13thWell several more days have passed and the team has finished the prep work for the floor and today they brought in the trucks of concrete to finish the floor and this stage of the build. The builder under-estimated the quantity and ran short to finish the floor by about half a truck. So they ended the pour by mixing the rest by hand. Apple explained he made the floor thicker than he planned and that he did not take the extra thickness into account when he ordered the concrete.pklongballFeb 14, 2009
|
|

8 February 2009A long view of the site as it looked today.pklongballFeb 08, 2009
|
|

Overview Front We are almost ready to pour the CPAC concrete floor and end phase one of the build.pklongballFeb 08, 2009
|
|

Mrs PK the "Supervisor"Sunday, Feb 8, 2009 Almost all of the sub-floor precast panels are in place. The builder's order was about 15 panels short. Not a big deal as he can get more quickly to fill the open spaces and get the floor poured this next week then it's on to the roof steel and roofing and the walls.pklongballFeb 08, 2009
|
|
|

|
|
|