Home > User galleries > pklongball > Phala - "The Floor comes next"

P1261711.JPG
26 Jan. 2009Another day on the job and there is work to be done.pklongball
P1261712.JPG
26 Jan. 2009The site on Monday after 3 days of watering and curingpklongball
P1261713.JPG
26 Jan. 2009The crew is hard at it stripping off the wood forms exposing all the new concrete beamspklongball
P1261714.JPG
26 Jan. 2009Stripping off all the wood forms is next on the list to get the site ready for the floor panels.pklongball
P1291715.JPG
29 Jan. 2009Overview of the site just after the first delivery of floor panels.pklongball
P1291716.JPG
29 Jan. 2009The crew is taking a short break waiting for the next batch of concrete from the mixer.pklongball
P1291717.JPG
29 Jan. 2009This view shows the floor panels near the back of the house and the crew busy filling the first 10 of the columns.pklongball
P1291719.JPG
29 Jan. 2009The floor panels were delivered today. We have 3 different lengths to span the areas needed.pklongball
P1291720.JPG
29 Jan. 2009Overview of Mr. Termite spraying the ground under the house. This first application of termite chemical will be followed with another using the tubing system just after house completion and then every six months after. The current contract is for 3 years.pklongball
P1291722.JPG
29 Jan. 2009Just another view of the final result of the tubing install and some debris that will be removed before the floor goes in place1 commentspklongball
P1291724.JPG
29 Jan. 2009View just after the install of the tubing. A first application of the chemical was applied using a high pressure sprayer.pklongball
P1291725.JPG
29 Jan. 2009The install called for the Termite Team to install 10 zones of tubing. The zones were divided into 4 exit points around the foundation. If these look long , they are intending to be cut to a proper length when the final finish is applied to the wall.pklongball