Home > User galleries > chiyman > Chiyman's Low Cost House - Part 4 - First Floor Columns and GF blockwork

Last additions - Chiyman's Low Cost House - Part 4 - First Floor Columns and GF blockwork
DSCF5056.JPG
Good quality hardwood doorframe squared and supported before blockwork constructionchiymanJan 18, 2011
DSCF5055.JPG
First Floor Columns completed with Formwork removedchiymanJan 18, 2011
DSCF5054.JPG
Formwork for window lintel being constructedchiymanJan 18, 2011
DSCF5053.JPG
Columns constructed and window lintel for full height windows in place. The formwork will be removed once the concrete has curedchiymanJan 18, 2011
DSCF5052.JPG
chiymanJan 18, 2011
DSCF5061.JPG
Blockwork wall and bottom window lintel in placechiymanJan 18, 2011
DSCF5060.JPG
Door lintel formwork being put in placechiymanJan 18, 2011
DSCF5059.JPG
Blokwork wall with bottom window lintel steelwork being placedchiymanJan 18, 2011
DSCF5058.JPG
First floor columns complete, roof ring beam being constructed from steel.The roof ring beam is commected to the top of the columns by welding to the reinforcement protrouding form the top of the column. An RC beam will also be constructed as a lintel for the large upstairs bedroom window - the formwork for this can be seen. I tried to make sure that safety on site was as good as possible but Thai people have their own way of doing things!! Fortunately he didnt fall off and indeed the whole project has been completed without any accident on site.
chiymanJan 18, 2011
DSCF5057.JPG
Placing blockwork - note the steel reinforcement placed in the columns and embedded in the cement between each course of block.chiymanJan 18, 2011
   
22 files on 2 page(s) 2