Home > User galleries > pklongball > Phala - "The Roof Tile"

P3161872.JPG
16 March 2009Soon this stack of tile will be on the roof.pklongball
P3191879.JPG
19 March 2009So we had a good bit of work on the tile today. I would say about 3 days should get the majority of tile in place.pklongball
P3191878.JPG
19 March 2009This is a front view at about 4 in the afternoon. The roof tile crew did a nice days work.pklongball
P3191891.JPG
19 March 2009A view from the back patio area looking into the kitchen door and office area window.pklongball
P3211897.JPG
21 March 2009A little different view from the land next doorpklongball
P3211900.JPG
21 March 2009Front left view of the house and roof tilepklongball
P3211901.JPG
21 March 2009Back view of house and roof with the tile.pklongball
P3211905.JPG
21 March 2009Here I was just showing the roof steel with the foil under the tile. pklongball
P3261938.JPG
26 March 2009Another day and more of the roof tile is completed. Almost finished nowpklongball
P3281957.jpg
28 March 2009This roof valley will be completed in short order and should have a nice tight fit of tilespklongball
P4011988.JPG
1 AprilHere we have one of the roof valleys after it's finished. Nice looking job of cutting and fitting the tilespklongball
P4011989.JPG
1 AprilThe look of the tile just about sundown with the edges now almost finishedpklongball
21 files on 2 page(s) 1