Chiyman's Low Cost House - part 1 - substructure and ground beams
|
|
|
The workers camp with excess concrete being used for a place for washing. The workers like to stay in the tent which they regarded as more professional than constructing their own accommodation!!chiyman
|
|
The Electical Authority man with his wife - they were perfectly charming. He did his work very professionally and also helped with the breaker installation. Thanks.chiyman
|
|
Ground beams being placed in position on top of the below groung columns - lots of water applied to consolidate the footings.chiyman
|
|
I am the proud owner of Brand new concrete mixerI bought this in town and had it loaded onto the back of my pickup. Was a bit concerned while driving it to the house especially when I needed to go up some steep hills. The journey took much longer than usual!!chiyman
|
|
Ground beam formwork in placechiyman
|
|
Sand and Stone delivered and ready for construction of the ground beams - Cement delivered in bags in a weatherproof area.chiyman
|
|
Formwork and reinforcement placed and ready for concrete pour the next daychiyman
|
|
Formwork for ground beamsI checked carefully to ensure that there was sufficient space between the reinforcement and the wooden formwork. Some adjustment was necessary. If the steel dosent have a concrete cover (of sufficent thickness) then it will be exposed to the atmosphere and will corrode. At best this will show as a dirty brown mark on the exterior of the structure and at worst, over time could cause structural failure.chiyman
|
|
All set for construction of the ground beamschiyman
|
|
Awaiting arrival of the workers for construction of the ground beamschiyman
|
|
All set and ready for mixing concrete for the ground beamschiyman
|
|
Sand, Stone and cement being delivered by the local supply company. They also produce precast products such as poles and pipes etcchiyman
|
|