Home > User galleries > chiyman > Chiyman's Low Cost House - part 1 - substructure and ground beams

DSCF4635_resize.jpg
Land purchased and area leveled ready for construction after settling.chiyman
DSCF4637_resize.jpg
Another angle on the levelled land awaiting construction in 7 months time - after the rainy season which will allow the land to settle.chiyman
DSCF4896_resize.jpg
Steel for the Footings placed with Concrete pipes for the below ground sections of the columns supported with yuca poles.chiyman
DSCF4898_resize.jpg
Footing in place, supported on clay bricks to allow concrete to flow arround the pad. Pad overall dimension 1.5m x 1.5m steel cage dimension 1.3m x 1.3 m.I had to complete the first stages of the construction quickly so decided to use the conceret pipes to form the below grade section of the columns. This allows backfilling of the footing as soon as the concrete had hardened and avoided the need to construct wooden forms.chiyman
DSCF4899_resize.jpg
Another view of the footings before the concrete pour.chiyman
DSCF4900.JPG
Clearing the way for the Concrete truck. (The chaps who had dug the holes had left the soil right by the edges of the holes).chiyman
DSCF4901.JPG
Clearing the way for the Concrete truck. Next stage construction materials in the foregroundchiyman
DSCF4903.JPG
Clearing the way for the Concrete truck. Workers Camp in Background!!!chiyman
DSCF4904.JPG
Getting everything straight and levelled before the big concrete pour.chiyman
DSCF4906.JPG
Getting everything straight and levelled before the big concrete pour.chiyman
DSCF4907.JPG
Getting everything straight and levelled before the big concrete pour.chiyman
DSCF4908.JPG
First of 3 Concrete truck arrives. Pour direct to the footing and also filling the concrete pipes which form the below ground section of the main building columns.chiyman