happy builder

 Coolthaihouse Photo Gallery

Construction Photos
Home > User galleries > Max&Bee-in-CM > Main House - Roof Metal

IMG_9985.JPG
Strengthening of the roof beginsMax&Bee-in-CM
IMG_9976.JPG
More metal ordered for roof reinforcementMax&Bee-in-CM
IMG_9958.JPG
Soil infill and roof work progresses togetherMax&Bee-in-CM
IMG_0129.JPG
More metal ordered for roof reinforcementMax&Bee-in-CM
IMG_0127.JPG
Soil infill and roof work progresses togetherMax&Bee-in-CM
IMG_0588_-_Sagging.jpg
The metal beams begin to sag under the weight of the tilesMax&Bee-in-CM
IMG_0814.JPG
Repairing the roofThe roof structure is being converted into a truss systemMax&Bee-in-CM
IMG_0617.JPG
Jacking up the sagging beamA few car jacks were used to straighten out the sagging beams, before the truss structure was welded into placeMax&Bee-in-CM
IMG_0616.JPG
The (incompetent?) roof metal guy thinks about how to jack up the roofMaybe incompetent is too strong a word - but he was quick to assign blame to poor quality metal, bad architect, bad engineer, CPAC tiles too heavy, roof too big, etc - everyone except himself.Max&Bee-in-CM
IMG_0612.JPG
Beams for making the truss structure are paintedMax&Bee-in-CM
IMG_0871.JPG
Welding cross beams for the trussMax&Bee-in-CM
IMG_0833.JPG
Installing beams for the side trussMax&Bee-in-CM