Interior WallThe start of the interior wall laying process. dozer (1 votes)
|
|
Oversize Cinderblock Laying ProceedsThe block laying proceeds on top of the second horizontal beam. Note the vertical vent PVC pipes extend upward through designated holes in the blocks.
dozer (1 votes)
|
|
Rebar Frame Work for Beam #3This is the rebar framework which will go in the top horizontal beam, located at a distance of 3 m. - 3.2 m from the floor level.
dozer (2 votes)
|
|
Electric Power PointMost electric face plates only have one row of receptacles. These Panasonic face plates give two rows. The house has a abundant supply of outlets. dozer (1 votes)
|
|
Water TankNote the rebar that surrounds the tank and extends out of the walls. This was a part of the rebar meshing used to re enforce the structure. The interior cinderblock is formwork but will remain in the finished structure. It will be rendered with a waterproofing agent as was the cement in the walls of the tank. dozer (1 votes)
|
|
Depth IndicatorA depth of render indicator is plastered in place prior to render application. This is used to determine the thickness of the render to be applied. dozer (1 votes)
|
|
Glass BlocksThis shot shows glass blocks being installed and the use of plastic spacers at the intersections to keep the blocks equidistant (spacing of 1 cm). dozer (1 votes)
|
|
A lintel will be poured on top of each section of decorative glass blocks as if they were a window. No load bearing capabilities for the glass blocks are assumed.
dozer (1 votes)
|
|
Front of HouseThe front of the house. Note the window openings each have a vertical rebar column on each side. A 10 cm beam will be poured across the top of the window and door openings at a 2.1 m distance from the floor.
dozer (1 votes)
|
|
Concrete Compressive Strength VerificationThis report shows the results of the compressive strength test on the concrete samples taken by the quality control staff. It is a good verification as the quality of the concrete used in the foundation is significant.dozer (2 votes)
|
|
Bathroom View 3dozer (2 votes)
|
|
Fascia BoardThe fascia board being applied. It fits nicely in a groove under this CPAC monier roof tiles. The bird guard is applied while this fascia board is being applied. dozer (1 votes)
|
|