15 AprilThis is the last day of Songkran and we actually have 6 or 7 workers on site. Three of them are now adding the wood work to the gables and in this view the vents are being built.pklongball (0 votes)
4 AprilFrom the right front corner we can see a hip area that needs the cap tiles and this will just about complete the tile work. A few more in the areas close to the bottom of the two big gables and then the gable work and the roof will be finished.pklongball (0 votes)
4 AprilAnd from the back right corner we can see gables that need finishing and the master bedroom door opening and the back verandapklongball (0 votes)
4 AprilThis shot of one of the valley areas of the roof. Nice job on all the valleys and I would have expected this as I have seen this man's work on other builds my builder has donepklongball (0 votes)
4 AprilAnd now the back left corner view showing us the long roof valley that was done very well in my opinion. The tile fitter spent a lot of time cutting the tile to get a good tight, straight line down this valley.pklongball (0 votes)
4 AprilFrom the left front view we can see the roof gable is the next finish that needs to be done.pklongball (0 votes)
4 AprilIn this view from the driveway entry we can get a heads on view of the now 99% finished tile.pklongball (0 votes)
1 AprilLay brickie working her way up another interior wall. Not too much more block and the walls will be uppklongball (0 votes)
1 AprilLiving room widow rough opening with the first coat of cement on it.pklongball (0 votes)
1 AprilA view of the first coating of cement to start squaring up the window openingspklongball (0 votes)
1 AprilHere we have the clean up lady. When she's not busy mixing mud or carrying stuff then the builder has her cleaning debris and sweeping the area.pklongball (0 votes)
28 March 2009This roof valley will be completed in short order and should have a nice tight fit of tilespklongball (0 votes)