P5202259.JPG
20 MayBack of the house looking at the master bedroom door and the now painted walls. First coat is a primer coatpklongball00000
(0 votes)
P5202260.JPG
20 MayAnother angle of the tile in the bedroompklongball00000
(0 votes)
P5202262.JPG
20 MayNow we have floor tile in the master bedroom. This tile has a simulated woodgrain look.pklongball00000
(0 votes)
P5212270.JPG
21 MayAnother view of Sparky the pole jockey. I don't know if you can see the heavy rope he has used around his waist and around the pole as a safety. pklongball00000
(0 votes)
P5212271.JPG
21 MayThis is a view that you don't see every day. Sparky is up on our pole and he is adding some steel brackets and U bolts to secure the PVC and the PE pipe to the pole. He asked me if I wanted this and I of course said yes. This type of thing will also be used under the house in the crawl space where the PE comes up from the trench and goes to the load center conduit under the floor.pklongball00000
(0 votes)
P5202253.JPG
20 MayHere we can see the finished PE pipe that has 2 phone cables. One will be active and the second a backup pair.pklongball00000
(0 votes)
P5202254.JPG
20 MayI wanted to show the stubbed up end of the third PE pipe that Sparky ran. This pipe will have the poweer for the wall lighting and automatic gate opener.pklongball00000
(0 votes)
P5202257.JPG
20 MayThis is one of the paint crew and he was painting the wood trim with a primerpklongball00000
(0 votes)
P5202258.JPG
20 MayToday we have a view of the back of the place and we have a new coat of white primer paint to seepklongball00000
(0 votes)
P5192248.JPG
19 MayAnother view of the two cable feeders. Before the needed length was pulled in , tile man 1 went under the house to help pull. So we ended up with 3 pulling and one feeding. But in about 20 minutes or so it was done.pklongball00000
(0 votes)
P5192249.JPG
19 maySparky started feeding in the NYY cable and his helper was under the house pulling it. After about 15 meters the cable stopped and his mate was almost spent trying to pull the cable alone. Sparky enlisted the help of the tile installers. In this view tile man 1 is helping to feed cable and tile man 2 went under the house to help pull.pklongball00000
(0 votes)
P5192243.JPG
19 MayHere we can see the NYY cable and the now attached pull rope.pklongball00000
(0 votes)