Ground floor slab formwork almost completed.chiyman00000
(0 votes)
DSCF4952.JPG
Ground floor slab reinforcement placed and tied into the ground floor beam steelwork.chiyman00000
(0 votes)
DSCF4951.JPG
Bathroom drainage connections placed befor pouring the ground floor slabchiyman00000
(0 votes)
DSCF4960.JPG
The connection pipe from the toilet to the collection tank.chiyman00000
(0 votes)
DSCF4959.JPG
Toild waste receptical and blue pipe which will discharge water from the shower and wash hand basin.chiyman00000
(0 votes)
DSCF4958.JPG
Ground floor Bathroom waste water pipework placed in position.chiyman00000
(0 votes)
DSCF4957.JPG
Ground slab formwork completed and ready for the pour. Concrete mixer, sand, stone and cement ready.chiyman00000
(0 votes)
DSCF4956.JPG
Ground slab formwork completed and ready for the pourchiyman00000
(0 votes)
DSCF4965.JPG
Groundfloor formwork completed. Our construction workers lived in the tent which can been seen in the picture. They considered this to be more "professional" than constructing their own temporary accommodation!!chiyman00000
(0 votes)
DSCF4964.JPG
Ground floor formwork completedchiyman00000
(0 votes)
DSCF4963.JPG
Ground floor formwork completedchiyman00000
(0 votes)
DSCF4962.JPG
Ground floor slab formwork completed and ready for concrete pour the next day. The bathroom (with the blue pipe sticking out) will be formed at a lower level and cast seperatelychiyman00000