Bad Cement - Expiration DateCement bags normally have a production date somewhere on there. If you can find it, it makes your job easier during purchasing, as you can check it then.dozer (0 votes)
|
|
Bad Cement - IndicationsThis is an example of stale cement. Cement has a shelf life of about 2 months and after that it becomes non powdery and sticks together much like this large size clump indicates. Workers will often try to use this cement with out saying anything but it is low quality and can be returned if it came from the store this way. dozer (0 votes)
|
|
Research - Color PigmentColoration of the render coat is impacted by a number of factors - the color of the fine aggregate sand use, the color of the cement, and the amount and ratios of pigment, cement, sand and water used. There several hundred test batches done to ensure the resultant color would match the design. This shows some test batches where color render was applied to cinderblocks.dozer (0 votes)
|
|
Storage Room Midway through a ProjectThe storage room will reach maximum capacity about 1/2 way through any given project. The 1/2 way point is about the time the exterior roof is completed. After this some materials can be kept in the house.dozer (0 votes)
|
|
Storage RoomAll of the building materials are kept in a whether proof storage room.dozer (0 votes)
|
|
Pesticide applicationThis is the pesticide used for termite termination, brand 'kornonam', which mixes with water 1 part to 19 parts. This seems to be a very and simple and effective preventative measure. dozer (0 votes)
|
|
Pesticide applicationOK, I never said anything about high tech. This is the pesticide being applied.dozer (0 votes)
|
|
Rough Coat RenderThis shows a color coat of render being applied over a dried rough coat render. There is a certain technique which we employed after some initial missteps to get the block outline not to show through to the color coat.dozer (0 votes)
|
|
Blocks being LaidHere the cinder blocks are being laid according to a 'straight' line of fishing wire which is used to keep the rows level.dozer (0 votes)
|
|
6mm Tie-in RebarThis shows a piece of 6mm rebar which sits in between blocks as they are laid and goes through the column framework. This is used to secure the blocks on either side of the column together.dozer (0 votes)
|
|
Wall Section with OpeningsThis shows a section of the perimeter wall, with column openings each 2.5 m. Notice that the columns are always poured after the blocks are laid for better adhesion. dozer (0 votes)
|
|
Rebar Framework for Top BeamThe rebar used in the top beam is 2 strands of 9mm rebar with 'chain' sections to keep the bars equidistant.dozer (0 votes)
|
|