IMG_8505.jpg
Support member to add strength to the wall section, along with view of more drainage pvc pipes. dozer00000
(0 votes)
IMG_8502.jpg
Placing of 3 inch PVC pipe used to aid drainage, placed at the lower level of the wall. dozer00000
(0 votes)
IMG_8484.jpg
Preparing for the pour of the upper ring beam. The metal is being affixed in place prior to the form work being affixed. dozer00000
(0 votes)
IMG_8483.jpg
Cinder block wall prior to render. Note that he columns were poured after the blocks were laid to prevent cracking/weakness at the junction. dozer00000
(0 votes)
DSC02458.JPG
The footing for the bathroom. The ground beam will be on top of this.dozer00000
(0 votes)
DSC02451.JPG
The external bathroom footing with the rebar footing pad in place. dozer00000
(0 votes)
IMG_2834.JPG
Side view of the house, still partially finished. The bathroom is in the rear (with two glass blocks). dozer00000
(0 votes)
IMG_1771.JPG
Approximate wall thickness after rendering, about 8 cm. dozer00000
(0 votes)
IMG_1770.JPG
dozer00000
(0 votes)
DSC02675.JPG
The interior after the pour of the floor and walls rendered. The floor was poured 8 - 10 cm and broomed rough in preparation for floor tiles. dozer00000
(0 votes)
DSC02599.JPG
After the exterior walls have been rendered. dozer00000
(0 votes)
DSC02582.JPG
The exterior prior to rendering the surface. dozer00000
(0 votes)