Footing Hole496 viewsA footing hole with metal frame work. Each hole was 1 meter square by about 40 cm. deep. In this design there are only two foundation columns in the patio. Throughout the rest of the house there are footing and then a ground beam on top of the footings. The walls are load bearing with columns inside the wall material itself.
dozer
|
|

447 viewsThis shows the relative size of the large cinderblocks along with the crushed stone aggregate that will be used in concrete within every other hole of the blocks. The walls thus created will be load bearing walls, every other hole will be filled with 12mm metal rebar and concrete to make the embedded support columns.
dozer
|
|

External From Front Left443 viewsThe roof is a 28% angle. This particular house will be 84 square meters inside, although it looks bigger.dozer
|
|

Kitchen from Entry Way422 viewsNotice the simple two level ceiling and the open design of the kitchen area, separated only by the wall color and floor tiles. dozer
|
|

Form work415 viewsThis shows the nearly completed form work.dozer
|
|

Cinderblocks used as Supports for Ground Beam412 viewsSmall cinder blocks are used as permanent supports (on the inside) for the ground beam. These will remain as a part of the foundation after the ground beam is poured.
dozer
|
|

Concrete Compressive Strength Verification411 viewsThis report shows the results of the compressive strength test on the concrete samples taken by the quality control staff. It is a good verification as the quality of the concrete used in the foundation is significant.dozer
|
|

Interior Wall use of Plumb Bob388 viewsA plumb bob is used to set a vertical line for the interior walls that will be brought 'true' during the render application. Straight lines are use vertically and horizontally.dozer
|
|

CPAC Pour of Ground Beams387 viewsCPAC ready mix cement pour of ground beams. 280 KSC (kilometers per square centimeter) concrete was used as in the floor. CPAC is better than hand mix for large areas since it is poured as a homogeneous unit.
dozer
|
|

Great Room from Rear385 viewsdozer
|
|

Ground Beam383 viewsThe ground beam which sits on top of the footings will be 45 centimeters high by 25 centimeters wide. This shows the metal rebar frame work which will be encased in concrete to make the ground beam.
dozer
|
|

Ground Beam Rebar Frame381 viewsThe rebar framework to support the ground beam.
dozer
|
|