Most viewed - chiyman's Gallery |
|
|

Unloading Precast concrete slabs33 viewschiyman
|
|

Still waiting for concrete to cure!32 viewschiyman
|
|

Placing the first floor pre cast slabs, removal of first floor beam formwork and placement of first floor slab mesh reinforcement.32 viewschiyman
|
|

First Floor Columns completed with Formwork removed32 viewschiyman
|
|

The roof tiles being installed32 viewschiyman
|
|
|

A hoist put in position for lifting concrete to first floor for final casting of the first floor slab on top of the precast slabs.31 viewschiyman
|
|

Pre cast concrete slabs used to form the first floor being delivered31 viewschiyman
|
|
|

Formwork for window lintel being constructed31 viewschiyman
|
|
160 files on 14 page(s) |
 |
 |
 |
 |
 |
 |
 |
11 |  |
 |
|

|
|
|