Ground beams being placed in position on top of the below groung columns - lots of water applied to consolidate the footings.91 viewschiyman
|
|
The Electical Authority man with his wife - they were perfectly charming. He did his work very professionally and also helped with the breaker installation. Thanks.87 viewschiyman
|
|
A happy constructor with a Pepsi!85 viewschiyman
|
|
Finishing the first floor slab concrete83 viewschiyman
|
|
Footings poured and concrete pipes cropped to the correct level for further constuction and attachment of the ground beams. This method saved a lot of time.81 viewschiyman
|
|
Ditto previos photograph78 viewschiyman
|
|
Footing in place, supported on clay bricks to allow concrete to flow arround the pad. Pad overall dimension 1.5m x 1.5m steel cage dimension 1.3m x 1.3 m.76 viewsI had to complete the first stages of the construction quickly so decided to use the conceret pipes to form the below grade section of the columns. This allows backfilling of the footing as soon as the concrete had hardened and avoided the need to construct wooden forms.chiyman
|
|
Clearing the way for the Concrete truck. (The chaps who had dug the holes had left the soil right by the edges of the holes).74 viewschiyman
|
|
Another view of the footings before the concrete pour.74 viewschiyman
|
|
Backfilling and cutting trench for the ground beams.70 viewschiyman
|
|
Backfilling the footings the next day68 viewschiyman
|
|
|