21 March 2009212 viewsHere we can see a wall and the lintel now poured and the blocks going up on each side of what will be a big slider window.pklongball
21 Feb 2009211 viewsLongshot of the roof steel progress.pklongball
21 March 2009210 viewsHere I was just showing the roof steel with the foil under the tile. pklongball
July 9210 viewsToday we were graced with the presence of the long awaited plumber. He is doing his thing and now the guest bath has all the valves and fixtures in placepklongball
June 30209 viewsA look at the rear of the placepklongball
28 April208 viewsAt the same time as the ceiling crew arrived the waterman finally made a return and started his part of the job. Here we can see the now installed toilet pipes and the beginning of the shower and sinks drain linespklongball
19 March 2009207 viewsThe bedroom wall looking onto the rear patio area and it's prepared for the lintel. You can also see some of the pvc work for plugs and suchpklongball
19 March 2009207 viewsAnother view of the kitchen wall and the electric pvc and boxes for some plugs.pklongball
29 Jan. 2009206 viewsOverview of Mr. Termite spraying the ground under the house. This first application of termite chemical will be followed with another using the tubing system just after house completion and then every six months after. The current contract is for 3 years.pklongball
28 April206 viewsHere we see and assortment of supply and drains. The open wall cavity allows them to put in both bathrooms at the same time. Only a minimal amount of pipes are buried in the floor tile.pklongball
June 26206 viewsWe now have some tile added to the wall around the HOB. The colors are green and yellow and whitepklongball
1 April205 viewsLay brickie working her way up another interior wall. Not too much more block and the walls will be uppklongball