P1221688.JPG
22 Jan 2009184 viewsOne of the 4 trucks to make the pour and an overview of the bathroom floor area before the pourpklongball
P1291716.JPG
29 Jan. 2009184 viewsThe crew is taking a short break waiting for the next batch of concrete from the mixer.pklongball
P2031738.JPG
3 Feb 2009184 viewsA little push here and a grunt there and the concrete panel gets moved into position. No high tech machines here just plenty of grunt workpklongball
P3061819.jpg
6 March 09'184 viewsTwo of the roof crew welding in the small cross-members to the support channels. The square tube will be the support for the roof tile.pklongball
P8122662.JPG
August 12184 viewsA look at my now functional Grundfos pump. Two weeks of use and I am more than happy with the supply from this unit.pklongball
P2031737.JPG
3 Feb 2009183 viewsCarrying the panels from the stack to the house floor takes 4 Thai men and some sweat. They only have about 60 more to go.pklongball
P3261927.JPG
26 March 2009183 viewsAnother view of the panel with door off and you can see the spot for the main breaker and 24 MCB'spklongball
P4292065.JPG
29 April183 viewsMaster bath plumbing is now roughed-in. Minimal pipes in the floorpklongball
P4292073.JPG
29 April183 viewsNow a view from the crawl space opening and we can see the finished rough in for the bath pipingpklongball
P4292072.JPG
29 April183 viewsAs the pipes exit the opening going to the septic and drain pipes. PLEASE NOTE THE U_TRAP NEAR THE OPENING! There are two of these on the shower floor/sink drain lines from each bath roompklongball
P4292071.JPG
29 April183 viewsMore of the pipes as they come to the yet to be installed sewer pipe.pklongball
P2131761.jpg
Friday the 13th182 viewsThe floor pour as of about 1230 with just the front balcony area to finishpklongball