Most viewed |
First floor columns complete, roof ring beam being constructed from steel.44 viewsThe roof ring beam is commected to the top of the columns by welding to the reinforcement protrouding form the top of the column. An RC beam will also be constructed as a lintel for the large upstairs bedroom window - the formwork for this can be seen. I tried to make sure that safety on site was as good as possible but Thai people have their own way of doing things!! Fortunately he didnt fall off and indeed the whole project has been completed without any accident on site.
chiyman
|
|
|
Preparations44 viewsAlways thinking of the next step and keeping people busy.
Here I clean up for measuring of the future pool/guest house.
Maseratimartin
|
|
|
|
Drill Rig with Drilling Shafts44 viewsThe drilling rig. The shafts in the foreground are for drilling and attach to the trucks drill harness. dozer
|
|
Drill Rig Set Up44 viewsThe rig used to drill the hole with the shaft harness upright and in position. dozer
|
|
A Melted PVC Joint44 viewsThe PVC joints for the piping that brings the water up from the pump are melted into place. dozer
|
|
Lowing PVC into Place44 viewsHere a grooved section is being lowered into place. dozer
|
|
Taping a Joint44 viewsTaping a joint on the interior ceiling. The joints are taped, plastered and sanded for a smooth finish. dozer
|
|
Shelving Unit44 viewsThis opening is designed for another shelving unit (Kitchzo). dozer
|
|
Hardware to Support Upper Cabinets44 viewsThe wall mounting to support the upper cabinets. The electric is for above and below florescent lighting.dozer
|
|