Mixing equipment122 views2 Jan. 09' The build crew brought in a mixer and other materials needed for the foundation build starting Monday the 5th.pklongball
31 May122 viewsA view from the veranda looking over to the pump house construction and the rebar columns that were put in yesterday.pklongball
2 June122 viewsThe ladies get the job of tieing all the steel to the rebar to form the cagepklongball
July 9122 viewsSparky hard at it wiring up the load center.pklongball
August 12122 viewsThe gate is almost finished. A coat of paint to the whole thing will top it off nicely.pklongball
A Visit last week back to Thailand shows further Demolition122 viewsWe had to take a trip back to Thailand to sign some bank & land documents and visited the build site and the guys had been back to further clear some of the old house.