Supervision126 views5 Jan 09 Here we have some dedicated "sidewalk" supervisors getting close up to the work.pklongball
Footings and Columns126 views10 Jan 2009 The last view of the open holes. Next step is to fill in and start making the rebar forms for the beams joining all columns together.pklongball
26 March 2009126 viewsA general view looking to the bedroom door and two of the team discussing what beer they will drink with dinner tonight. One of the wall crew is up on the scaffolding working a wall that will be the back of the store roompklongball
5 May126 viewsThe ceiling boys were in today and they go more "rock" installed. Here we can see a square hole that will be a service access to the attic space.pklongball
27 October126 viewsWe decided we could not walk over the dirt/sand any longer and waiting for the grass is taking too long so we hired the tileman/wife team to pour about 18 square meters of concrete for a walking path to/from the house steps to the pump house area. The team will apply a sand wash finish matching the yellow back steps. We are paying them 100 baht per sq meter labor. We bought the materials they have the tools.pklongball
Putting good luck stuff in the foundation hole126 viewsMishark
Cinderblocks Form Work126 viewsThe cinder blocks are used as form work for the entire ground beam. The cinder blocks will remain after the pour and become part of the flooring material and the exterior walkway. dozer