Khun Apple measuring the layout135 viewsKhun Apple is just starting the measurement process for the house layout.
15 Dec.'08pklongball
|
|

More columns in place135 views5 Jan 09 Work continuespklongball
|
|

Meter install almost finished135 views10 Jan 2009 The meter and valves are encased in cement to prevent tampering and stealingpklongball
|
|

11 Jan 2009135 viewsHere we have the Mrs. watering the columns and dirt around them. She said if she puts enough water on all 31 columns in 6 months a house will grow. I hope she's right!pklongball
|
|
|

2 May135 viewsA view looking along the back wall and the partly buried drain pipes and boxes.pklongball
|
|

8 May135 viewsAnother view of the ceiling area and the complex of raceway, wires and conduitspklongball
|
|

Dec. 4th135 viewsOne more shot of the back yardpklongball
|
|

Walkway Pour135 viewsIn preparation for the walkway pour there is a rebar mesh put in place with spacing every 20 centimeters. dozer
|
|
|
|

finished view134 viewslooks ok from a distance ;-omikey3073
|
|