Front Exit141 viewsThe front exit onto the patio which is done with terracotta tiles. dozer
|
|
Water Flow Test and Drainage PVC141 viewsThe drainage PVC has been installed in the proper places to allow the water to exit the site, as evidenced during this flow test. dozer
|
|
|
Spotlights for nighttime badminton and bug collecting140 viewssomdet
|
|
|
|
Column centers140 viewsAfter the initial measuring and stringing the nylon line Khun Apple and crew find the approximate centers for the columns
15 Dec.'08pklongball
|
|
Ready to build on140 viewsThis is the final view of the plot before any work on the wall or the house. We have a 50 percent share of that electric pole in place.
Nov.'08pklongball
|
|
2 Jan. '09140 viewsThis is the view today. The builder brought in the needed equipment for the foundation concrete mixing. Lumber, sand, gravel and other items. First step was to line the bottoms of the holes with a layer of concrete to place the footing rebar on. This process happened over the weekend in preparation for the raising/blessing on Monday the 5th.pklongball
|
|
Blessing Man140 views5 Jan 09 After the ceremony of praying over the food table and raising the columns Blessing Man sits in solitude in the middle of the site and makes some final chants and prayers during the first part of the pouring activity.pklongball
|
|
North & West house view140 viewsThis shows the view of the front (west elevation) and side (north) of the house when we had to return home last year.bngldsmth
|
|
Front & side view140 viewsAgain the front & side view of the house when we had to return home last year.bngldsmth
|
|