IMG_2438.jpg
ScrapThe part cut off, to be sold for scrap.dozerSep 28, 2011
IMG_2436.jpg
Metal ToppedThe top of the metal was cut off, here it is being smoothed. dozerSep 28, 2011
DSC05123.jpg
Original Wall with MetalAnother view of the original wall that will be raised. The metal will be topped and a new beam poured on top. dozerSep 28, 2011
DSC05120.jpg
Original View of Front WallThis is an original view of the front wall. To note the road had just been re-bulldozed, the lower total height of the wall is 75 cm and the top of the metal is at about 1.6 m. dozerSep 28, 2011
IMG_2891.jpg
Prep WorkThe top concrete layer had already been removed, here is some of the dirt dug in prep for pouring concrete. Forms are starting to be positioned. dozerSep 28, 2011
DSC05052.jpg
Original WellThe stone aggregate (used to line the line the well) footprint was eventually concreted over. dozerSep 28, 2011
IMG_2910.jpg
Troweling the SurfaceThe finished surface of the upper level of the pour with concrete all around the well. dozerSep 28, 2011
IMG_2892.jpg
Forming Sealing LayerThe forms and rebar are set in place to pour the upper level of concrete. The gutter is poured separately. dozerSep 28, 2011
IMG_2883.jpg
Forming GutterThe gutter will run along the exterior of the wall. Here rebar is placed to form the gutter. dozerSep 28, 2011
IMG_2881.jpg
Rerouted ElectricalSome electrical that ran encased in concrete prior needed to be re-routed. Add one to the reasons over time I don't like encasing anything in concrete. 1 commentsdozerSep 28, 2011
IMG_2875.jpg
Concrete RemovedAll of the old top concrete layer was busted out and removed.dozerSep 28, 2011
DSC01887.jpg
Original CrackThe original crack which was filled using wall putty a couple of time but kept re-appearing. dozerSep 28, 2011