DSCF4962.JPG
Ground floor slab formwork completed and ready for concrete pour the next day. The bathroom (with the blue pipe sticking out) will be formed at a lower level and cast seperatelychiymanJan 18, 2011
DSCF4961.JPG
The waste from the downstairs toilet will be collected in this tank formed from precast concrete rings - this one is 4 rings deep.chiymanJan 18, 2011
DSCF4972.JPG
Ground floor slab completed - the part nearest the concrete mixer will be brushed once it has semi cured.chiymanJan 18, 2011
DSCF4970.JPG
Everything ready for pouring the Ground floor slabchiymanJan 18, 2011
DSCF4969.JPG
Note the reinfocement for the ground floor slab (mesh) was tied onto the ground beam reinforcement for extra strength.chiymanJan 18, 2011
DSCF4968.JPG
placing pegs in the ground as a depth guide for the ground floor slabchiymanJan 18, 2011
DSCF4966.JPG
Materials for construction of the column formworkchiymanJan 18, 2011
DSCF4983.JPG
Pouring concrete into the column formwork - a highly manual process - effective though!!chiymanJan 18, 2011
DSCF4978.JPG
A delivery of Yucca poles freshly cut which will be used later for the first floor constructionchiymanJan 18, 2011
DSCF4975.JPG
Further ground floor to first floor column formwork constructionchiymanJan 18, 2011
DSCF4974.JPG
Ground floor slab completed. starting to build the formwork for the Ground floor to first floor columnschiymanJan 18, 2011
DSCF4973.JPG
Completed Ground slab brushed finish ready to accept floor tiling later onchiymanJan 18, 2011