Floor slabs being laid in place.Rick BFeb 06, 2008
|
|
Floor slabs (pan peun) are being laid for the first floor. These slabs will be covered with wire mesh and an additional 5cm of poured concrete.Rick BFeb 06, 2008
|
|
Rebar and forms for the second floor beams are bing assembled.Rick BFeb 06, 2008
|
|
First floor columns' forms are being assembled after the floor beams were completed.Rick BFeb 06, 2008
|
|
First floor columns are being fitted with formsRick BFeb 06, 2008
|
|
First floor beams are ready for the floor slabs (pan peun)Rick BFeb 06, 2008
|
|
Pre-stressed floor slabs for the first floor are being delivered direct from the factoryRick BFeb 06, 2008
|
|
Rebar for the first floor beams is being assembled in place.Rick BFeb 06, 2008
|
|
Forms and rebar for the first floor beams are ready for the concrete pour.Rick BFeb 06, 2008
|
|
Forms for the first floor beams are being assembled.Rick BFeb 06, 2008
|
|
Rebar and forms for the first floor beams are ready for the concrete pour. The top of the first floor is 115cm above grade to minimize problems should there ever be flooding.Rick BFeb 06, 2008
|
|
A typical footer and column placed on top of a single pile.Rick BFeb 06, 2008
|
|