11 March 2009One of the team using a saw to make a small channel in the block top to place the steel rebar between the blocks. This rebar is seated into the column and will hold the block wall to the columns for some more stabilitypklongballMar 12, 2009
|
|
11 March 2009We now have a small team of 2 men and a woman working on the walls. The first process will be to start a course up to a level just below any window openings or on a wall with no window about half way up. They will stop there to begin another wall. Once all the walls are started with the outer course we will call in he electrician to start installing the conduits in the cavities for all the plugs and switches.pklongballMar 12, 2009
|
|
11 March 2009Wall man fixes a wood form to the floor to make the corner walls for the store room bedroom wallspklongballMar 12, 2009
|
|
|
|
|
|
|
9 March 2009Moving the blocks from point A to point B is backbreaking and sweaty work and always the ladies get this job.pklongballMar 09, 2009
|
|
9 March 2009Another angle of the almost finished steelpklongballMar 09, 2009
|
|
9 March 2009Long shot of the roof at this stage. The tile will be coming soon.pklongballMar 09, 2009
|
|
9 March 2009And the welding continuespklongballMar 09, 2009
|
|