19 March 2009Living room wall to the veranda area and more of the wall and electric work.pklongballMar 20, 2009
|
|
19 March 2009This view is the exterior wall to the living room and the yellow pvc for the TV and electric outlets. Getting ready for a lintel here.pklongballMar 20, 2009
|
|
19 March 2009Another view of the kitchen wall and the electric pvc and boxes for some plugs.pklongballMar 20, 2009
|
|
19 March 2009Here we have the beginning of the wall between the kitchen and living room. We will end up with a countertop and pass thru window on both sides to allow getting beer and goodies to the living room.pklongballMar 20, 2009
|
|
19 March 2009This is one of 4 kids the wall man has. Typical young boy, school is out now and he wanted to be with dad to help him. I guess he got tuckered out and needed a nap.Normally the builder does not allow any kids on the job site except if the family has some issues.pklongballMar 20, 2009
|
|
19 March 2009I added this shot of this column to show a small problem we had in discussing the outdoor lights on the columns. Sparky had to chisel out the brick here and re-route the pvc to the outside of the column not the place he put it. Small but crucial to locate this decorative light on the correct side of the column. One of those confusion things when we were all talking and pointing where things should be placed.pklongballMar 20, 2009
|
|
19 March 2009The bedroom wall looking onto the rear patio area and it's prepared for the lintel. You can also see some of the pvc work for plugs and suchpklongballMar 20, 2009
|
|
19 March 2009Here we have a wall view of the master bedroom wall and preparations to make the concrete lintel. The method for any wall lintel is to shape the AAC blocks into small pieces and glue them into the cavity to allow poring of concrete for the beam.pklongballMar 20, 2009
|
|
19 March 2009Here we have a view of part of a wall and the pvc electric pipe install. This wall happens to be near the back of house that will have a window to look on the back yardpklongballMar 20, 2009
|
|
19 March 2009This is a front view at about 4 in the afternoon. The roof tile crew did a nice days work.pklongballMar 19, 2009
|
|
19 March 2009So we had a good bit of work on the tile today. I would say about 3 days should get the majority of tile in place.pklongballMar 19, 2009
|
|
17 March 2009The wall work, roof tile work and electric pipe work all going on at the same time.pklongballMar 18, 2009
|
|