4 AprilAnd from the back right corner we can see gables that need finishing and the master bedroom door opening and the back verandapklongballApr 04, 2009
|
|
4 AprilThis shot of one of the valley areas of the roof. Nice job on all the valleys and I would have expected this as I have seen this man's work on other builds my builder has donepklongballApr 04, 2009
|
|
4 AprilAnd now the back left corner view showing us the long roof valley that was done very well in my opinion. The tile fitter spent a lot of time cutting the tile to get a good tight, straight line down this valley.pklongballApr 04, 2009
|
|
4 AprilFrom the left front view we can see the roof gable is the next finish that needs to be done.pklongballApr 04, 2009
|
|
4 AprilIn this view from the driveway entry we can get a heads on view of the now 99% finished tile.pklongballApr 04, 2009
|
|
1 AprilLay brickie working her way up another interior wall. Not too much more block and the walls will be uppklongballApr 01, 2009
|
|
1 AprilLiving room widow rough opening with the first coat of cement on it.pklongballApr 01, 2009
|
|
1 AprilA view of the first coating of cement to start squaring up the window openingspklongballApr 01, 2009
|
|
1 AprilHere we have the clean up lady. When she's not busy mixing mud or carrying stuff then the builder has her cleaning debris and sweeping the area.pklongballApr 01, 2009
|
|
28 March 2009This roof valley will be completed in short order and should have a nice tight fit of tilespklongballApr 01, 2009
|
|
1 AprilHere we have one of the roof valleys after it's finished. Nice looking job of cutting and fitting the tilespklongballApr 01, 2009
|
|
1 AprilThe look of the tile just about sundown with the edges now almost finishedpklongballApr 01, 2009
|
|