P4041994.JPG
4 AprilAnd from the back right corner we can see gables that need finishing and the master bedroom door opening and the back verandapklongballApr 04, 2009
P4041995.JPG
4 AprilThis shot of one of the valley areas of the roof. Nice job on all the valleys and I would have expected this as I have seen this man's work on other builds my builder has donepklongballApr 04, 2009
P4041990.JPG
4 AprilAnd now the back left corner view showing us the long roof valley that was done very well in my opinion. The tile fitter spent a lot of time cutting the tile to get a good tight, straight line down this valley.pklongballApr 04, 2009
P4041991.JPG
4 AprilFrom the left front view we can see the roof gable is the next finish that needs to be done.pklongballApr 04, 2009
P4041992.JPG
4 AprilIn this view from the driveway entry we can get a heads on view of the now 99% finished tile.pklongballApr 04, 2009
P4011977.JPG
1 AprilLay brickie working her way up another interior wall. Not too much more block and the walls will be uppklongballApr 01, 2009
P4011978.JPG
1 AprilLiving room widow rough opening with the first coat of cement on it.pklongballApr 01, 2009
P4011979.JPG
1 AprilA view of the first coating of cement to start squaring up the window openingspklongballApr 01, 2009
P4011980.JPG
1 AprilHere we have the clean up lady. When she's not busy mixing mud or carrying stuff then the builder has her cleaning debris and sweeping the area.pklongballApr 01, 2009
P3281957.jpg
28 March 2009This roof valley will be completed in short order and should have a nice tight fit of tilespklongballApr 01, 2009
P4011988.JPG
1 AprilHere we have one of the roof valleys after it's finished. Nice looking job of cutting and fitting the tilespklongballApr 01, 2009
P4011989.JPG
1 AprilThe look of the tile just about sundown with the edges now almost finishedpklongballApr 01, 2009