Window_framing_parts1.jpg
Window Frame PartschangnoiJul 03, 2010
some_weird_thai_torture_machine.jpg
Some Weird Window Framing Torture MachinechangnoiJul 03, 2010
kitchen_window_frame_in.jpg
Kitchen Sliding WindowschangnoiJul 03, 2010
large_lounge_door_frame_in.jpg
Large Lounge Sliding DoorschangnoiJul 03, 2010
IMG_5140.JPG
Rented formworkWe rented it, not sure how much yet, will get the bill when we finish, but should be no more than 5,000 baht.Max&Bee-in-CMJul 02, 2010
IMG_5142.JPG
Ready for installWaiting to be installed into placeMax&Bee-in-CMJul 02, 2010
IMG_5148.JPG
Hammering the support sticksHave to ensure the formwork doesn't collapse when the concrete is pouredMax&Bee-in-CMJul 02, 2010
IMG_5153.JPG
Front porchThe front porch was incorrectly placed about 20 cm below the level of the house floor, so they had to redo it today.Max&Bee-in-CMJul 02, 2010
IMG_5160.JPG
Attaching the formworkLots of sticks are used to reinforce the formwork.Max&Bee-in-CMJul 02, 2010
IMG_5101.JPG
Ground beams rebar doneAll the rebar for the ground beams has been completed. Next step is the form work for the concrete.Max&Bee-in-CMJul 02, 2010
IMG_5071.JPG
Toilet, bathroom and bedroomLooking at the toilet in the front of the picture, the bathroom on the right, and the small bedroom next to it on the left.Max&Bee-in-CMJul 02, 2010
IMG_5079.JPG
The meals areaLooking at the meals area at the rear left of the house.Max&Bee-in-CMJul 02, 2010