Precast slab delivery/unloadingchiymanJan 18, 2011
|
|
Pre cast concrete slabs used to form the first floor being deliveredchiymanJan 18, 2011
|
|
A hoist put in position for lifting concrete to first floor for final casting of the first floor slab on top of the precast slabs.chiymanJan 18, 2011
|
|
Precast Slabs placed and formwork ready for pouring 50mm cover of concretechiymanJan 18, 2011
|
|
Placing the first floor pre cast slabs, removal of first floor beam formwork and placement of first floor slab mesh reinforcement.chiymanJan 18, 2011
|
|
Precast slabs in place forming the first floor - note the hole left is for the stairwell.chiymanJan 18, 2011
|
|
Lifting the precast ploor slabs into position on the first floor beams
chiymanJan 18, 2011
|
|
Roofing material and steel in the background.chiymanJan 18, 2011
|
|
First Floor Beams completed - formwork will be removed once the concrete has properly cured.chiymanJan 18, 2011
|
|
Completed First floor beams - awiting removal of formwork once the concrete has cured.chiymanJan 18, 2011
|
|
The larger white dog was in fact a male. I think the puppy was hungry. The dog then urinated on the puppy!! which made the construction worker owner rather cross!chiymanJan 18, 2011
|
|
Placing the steel reinforing mesh on the first floor precast slabschiymanJan 18, 2011
|
|