IMG_1224.jpg
Hand Scoring the PVC PipesHere the PVC pipe is grooved. The grooved pieces are not used in the first 8 meters (the top most part is non grooved). They are used at the bottom of the well to allow water to seep in and replenish the supply. dozerSep 26, 2011
IMG_1220.jpg
Prescored PVC Gets Thumbs DownThe well digger did not like these prefabricated grooved PVC pipes so we returned them. These are weaker and tend to collapse under pressure.dozerSep 26, 2011
IMG_1210.jpg
Lowing PVC into PlaceHere a grooved section is being lowered into place. dozerSep 26, 2011
IMG_1209.jpg
Cutting PVC for another TryThis was the first well attempt. The lower portion collapsed and was discarded under ground. dozerSep 26, 2011
IMG_1206.jpg
Lining the Bore HolePlacing a scored PVC pipe in the bore hole. dozerSep 26, 2011
IMG_1190.jpg
Deep Water Pump AssemblyPreparing the Franklin deep water pump to be submerged. dozerSep 26, 2011
IMG_1187.jpg
A Melted PVC JointThe PVC joints for the piping that brings the water up from the pump are melted into place. dozerSep 26, 2011
IMG_1182.jpg
Gas Melting StationHere is the rig they used to melt the PVC piping in place. dozerSep 26, 2011
IMG_1179.jpg
Franklin PumpA view of the pump without the exterior housing. dozerSep 26, 2011
IMG_1172.jpg
Drill Rig Set UpThe rig used to drill the hole with the shaft harness upright and in position. dozerSep 26, 2011
IMG_1169.jpg
Drill Rig with Drilling ShaftsThe drilling rig. The shafts in the foreground are for drilling and attach to the trucks drill harness. dozerSep 26, 2011
IMG_1167.jpg
Well Rig Gets to LandJust enough clearance to get into the land. This is a utility gate not used as a regular entrance, as it allows entry from someone else's land (currently unoccupied). Was slated for removal, glad we kept it.dozerSep 26, 2011