Bedroom InstallationThe first thing done is that the level of the lower step of the ceiling is established around the outside perimeter. The frame is being set up for a lower step which extends outward 60 centimeters and is 15 centimeters deep. dozerSep 27, 2011
|
|
Ceiling Secured RoomThis was the framing of the secured room where the ceiling is actually under a security level of metal welded together. The framework is tied to the security frame in this case, normally it is affixed to the roofing metal. dozerSep 27, 2011
|
|
Interior: FrameworkThe interior framework is established for the drywall sheeting to be installed. The very beginning of the process is establishing a straight line for every level to be used (if there is a step there would be the step level and the main level). This is done using the water clear tubing method and then setting the level lines in red chalk.dozerSep 27, 2011
|
|
|
|
|
|
|