Last additions - Chiyman's Low Cost House - Part 3 - First Floor beams and slab |
Finishing the first floor slab concretechiymanJan 18, 2011
|
|
Finishing the concrete pour of the First Floor slab. All concrete was lifted by the bucket load to the first floor using the pully. At about 10kg a load the number of movements was considerable!!chiymanJan 18, 2011
|
|
Unloading Precast concrete slabschiymanJan 18, 2011
|
|
Pre Cast Concrete slabs being unloaded directly to the first floor beamschiymanJan 18, 2011
|
|
First Floor Concrete beams with partial removal of formwork ready for receiving the precast first floor slabs. I was very happy with the quality of the beams.chiymanJan 18, 2011
|
|
Precast slab delivery/unloadingchiymanJan 18, 2011
|
|
Pre cast concrete slabs used to form the first floor being deliveredchiymanJan 18, 2011
|
|
A hoist put in position for lifting concrete to first floor for final casting of the first floor slab on top of the precast slabs.chiymanJan 18, 2011
|
|
Precast Slabs placed and formwork ready for pouring 50mm cover of concretechiymanJan 18, 2011
|
|
Placing the first floor pre cast slabs, removal of first floor beam formwork and placement of first floor slab mesh reinforcement.chiymanJan 18, 2011
|
|
Precast slabs in place forming the first floor - note the hole left is for the stairwell.chiymanJan 18, 2011
|
|
Lifting the precast ploor slabs into position on the first floor beams
chiymanJan 18, 2011
|
|
|
|
|
|