15 Jan 2009The lady part of the Beamteam is doing the tieing of the wire cages to get all the steel meshed together.pklongball
15 Jan 2009A little closer look at how two pieces of steel are meshed to the cage and bent in a hook fashion. I guess this allows for better connection in the concrete.2 commentspklongball
22 Jan 2009The concrete trucks arrive and the beam pour beginspklongball
22 Jan 2009A closer look at the pour crew hard at it.pklongball
22 Jan 2009One of the 4 trucks to make the pour and an overview of the bathroom floor area before the pourpklongball
22 Jan 2009A view of the forms and after they are filled.pklongball
22 Jan 2009This was a hard 4 hours of work and the pouring crew never took a water or food break that I saw. We bought lunch today!pklongball
22 Jan 2009Two concrete vibrators were used to pack the soup around and in the forms.pklongball
22 Jan 2009Behind that hat and red shirt is a cute little young girl. She had the duty of keeping the forms wet and the concrete from drying too fast.pklongball
23 Jan 2009The day after the pour and no one on site but a water lady. Her task is to show up once a day and wet down the area and keep the wood and cement wet. 3 days and they will remove the forms and begin work on the sub floor panels.pklongball