Rebar for the first floor beams is being assembled in place.Rick B
Forms for the first floor beams are being assembled.Rick B
Forms and rebar for the first floor beams are ready for the concrete pour.Rick B
Rebar and forms for the first floor beams are ready for the concrete pour. The top of the first floor is 115cm above grade to minimize problems should there ever be flooding.Rick B
First floor columns' forms are being assembled after the floor beams were completed.Rick B
First floor columns are being fitted with formsRick B
First floor beams are ready for the floor slabs (pan peun)Rick B
Pre-stressed floor slabs for the first floor are being delivered direct from the factoryRick B
Floor slabs being laid over first floor beams. The 6mm rebar seen embedded into the floor beams will be bent over the floor slabs and tied to the wire mesh laid over the floor slabs prior to pouring an additional 5cm of concrete on top of the floor slabs. This makes the finished floor ~ 10cm thick.Rick B