This is the starting shot, showing the plot leveled. The plot starts before the truck on the left and goes to the corner tree line. By this point the plot has already been leveled with fill dirt. (01-Jan-04)dozer
|
|
The perimeter wall is mostly completed. Still needs to be stuccoed. (27-Jan-04)dozer
|
|
The footing of a foundation column. (29-Feb-04)dozer
|
|
The house footing being formed. The footing of this house is about 20 inches tall. Inside the footing there is a metal substructure for strength. Off to the left of this footing you can see the hand tied metal substructure in preparation to pour another footing. To the right you see the form wood which is used to form the concrete pour. (05-Mar-04)dozer
|
|
The roof structure is built using heavy guage steel. The bigger pieces are 4 *2 inches and 1.6 mm thick. The smaller pieces are 1 by 1 inch and 1.6 mm thick. The roof tile will lie on the 1 by 1's, so they must be placed at the proper interval. Notice the cross beam supports which sit on top of the foundation posts. (13-Mar-04)dozer
|
|
Here the roof is partially tiled. The left shot shows the parking lot and patio. The right shot shows the main roof sections. Notice the aluminum drainage sheeting shown in the valley of the right hand picture: it is not really sufficient and will need to be supplemented later. (22-Mar-04)dozer
|
|
Here the roof is partially tiled. The left shot shows the parking lot and patio. The right shot shows the main roof sections. Notice the aluminum drainage sheeting shown in the valley of the right hand picture: it is not really sufficient and will need to be supplemented later. (22-Mar-04)dozer
|
|
This shows the rear door being framed. This is a repair job, since on the first attempt anchor nails were not used. This time nails will be placed at 4" intervals to anchor the door in place. (02-Apr-04)dozer
|
|
Stucco is what gives strength to the wall. Notice the thickness of the stucco shown here. This is the front exterior wall. (17-Apr-04)dozer
|
|
For each bathroom there are 2 septic tanks, dirty water and solid waste. Standard depth is 4 cement drainage rings, we use 5 which is better. This shot shows the solid waste septic on the left (servicing the small bathroom). The PVC which runs from the toilet is 4" in diameter. (22-Apr-04)dozer
|
|
This shot shows the front facia board which can be made of either wood or synthetic. We are using synthetic version which is formed from cement. Also note the wood framing is being put in place to attach the outdoor roofing material (grc sheeting). (25-Apr-04)dozer
|
|
The repaired roof valley. This was kind of a struggle due to inadequate valley aluminum which was then compensated for by using two pieces which are welded together. In any event the valley now looks good and there is no problem with water leakage. (02-May-04)dozer
|
|
|
|
|
|