Framework for Water TankAnother view of the frame work lattice which sits on top of 6 small footings. The framework is centered to be within the external wall using red bricks a spacers.dozer
|
|
Sika Water ProoferSika 'gan sum' waterproofing agent is added to the concrete mix.dozer
|
|
Framed and Poured External WallsAfter the floor pour is completed, the framework as seen is installed and the external walls are poured to a thickness of 15 centimeters. dozer
|
|
Simple SepticAnother view of a simple septic system with the waste pipe entering the concrete rings a a sufficient angle to allow flow. All of the septics are vented with the exhaust about the perimeter wall. dozer
|
|
Poured Underground Water TankThe poured underground water tank. The wall thickness is 15 centimeters. The dimensions are about 2.5 meters x .70 meter width by 1 meter depth. dozer
|
|
Undermount Stainless Kitchen SinkThe under mount stainless kitchen sink will sit under the custom cut granite counter top.dozer
|
|
Additonal Waterproofing Agent Applied to the BottomLanko K11 waterproofing agent is skim coated on the bottom (as shown) and will be applied to the sides of the enclosure as well. dozer
|
|
Framing for Top of EnclosureThe framing for the top of enclosure. Notice the rebar lattice with spacing of 20 centimeters. The lid/service opening is sized at 50 centimeters by 50 centimeters. There is an entry pipe, water level solenoid pipe, and exit pipe (to feed to the automatic water pump into the house). dozer
|
|
PVC Pipe Joined to Tested SectionThe pipe is being run from the automatic water pump to the previously tested in house section (note the cap on the pipe). Any exposed pipe section will be protected within a concrete pour. dozer
|
|
Finished Submerged Water TankThe finished tank, note the inbound water pipe (top), the outbound water pipe (center) and the electric inbound yellow conduit which feeds the solenoid valve within the tank. dozer
|
|
Lanko K11 WaterproofingThe cement skim coat which is evenly applied to the inside of the water tank as a double check against leakage. Note that the Sika water proofing which is mixed into the cement should be sufficient. dozer
|
|
Sloped Bathroom FloorsThe bathroom floors are sloped to allow water run off towards the drain pipe (shown on the left of the solids drain pipe). dozer
|
|
|
|
|
|