Tile CuttersTile cutters make a smoother cut than a grinder but are often not used in other projects.dozer (0 votes)
|
|
Counter TilesThe kitchen cabinet tiles are off white tiles spaced at 3 mm intervals. dozer (0 votes)
|
|
White Aluminum Window FramesThe windows opening are measured and the frames are then installed to fit. This is the more expensive 1.2 mm thick white aluminum. Note that most installations do not use the frame piece, which adds to the durability + is a decorative addition.dozer (0 votes)
|
|
Special Grout for Glass BlocksA special grout that is designed specifically for glass blocks is used in the trim areas around the blocks. dozer (0 votes)
|
|
Nearly Finished Counter CabinetsThe counter nearly finished. dozer (0 votes)
|
|
Ceiling in KitchenThe ceiling in the kitchen after the installation of the trim wood.dozer (0 votes)
|
|
Gate Being WeldedThe gate being welded. dozer (0 votes)
|
|
Level LineA long clear plastic tubing is used to create a level line which will be used to set the top level for the floor tiles. The tube is filled with water, on one end a line is marked at the water line. At a different area perhaps several meters away another mark is made (in is a two man process). This two independent marks will be at the same level and measurement can be made from this point downwards to determine the target level for the tiles. dozer (0 votes)
|
|
Kitchen PaintingThe kitchen being painted. The paint used was super shield (both primer and the finish coat). The kitchen and bathroom are semi gloss (washable) while the rest of the house are done in matte. dozer (0 votes)
|
|
Counter Prep for GraniteThe counter is being prepped for laying in the granite slabs. dozer (0 votes)
|
|
Slab put in PlaceHere the granite slab is set into place. The holes and edges are cut at the stone factory. The sinks were used by the factory to guarantee a perfect opening for the under mount sinks. The faucet holes will be drilled on site.dozer (0 votes)
|
|
Faucet HolesThe faucet holes are drilled on site by the granite people. A special bit is used and water is poured during the during the drilling process to avoid having the granite surface crack. dozer (0 votes)
|
|