DSC00152~0.jpg
Rear door being repaired. The first time the door was framed without using anchor nails and had to be redone. It is in the process of be reframed. (02-Apr-04)dozer00000
(0 votes)
DSC00139.jpg
Rear door framed and the side design of clear blocks. This side of clear blocks turned out to be poor placement, as when the door is open it blocks the light.dozer00000
(0 votes)
DSC00138.jpg
Bathroom window framed. Notice the cement base below the window and the use of red brick above.dozer00000
(0 votes)
DSC00136.jpg
Bathroom door being framed. This was a repair job. dozer00000
(0 votes)
DSC00131.jpg
These window frames show the how a cement base is placed above and below the window frame, and how the red bricks are used to level out the wall above the window. (28-Mar-04)dozer00000
(0 votes)
DSC00116.jpg
Starting to frame a bedroom door. A piece of 2 * 4 is used to keep the door in place.dozer00000
(0 votes)
DSC00112.jpg
Front door of house framed. There is a cement base above the door frame. (22-Mar-04)dozer00000
(0 votes)
DSC00104.jpg
Two windows framed. There is a 'leveled' cement base below the window frame and bricks are being used to level the wall to be even with the top of the frame. (13-Mar-04)dozer00000
(0 votes)
DSC05121.jpg
Finished roof, view from rear.dozer00000
(0 votes)
DSC05120~0.jpg
Finished roof, view from right front.dozer00000
(0 votes)
DSC05119~0.jpg
Finished roof, view from right front.dozer00000
(0 votes)
DSC04155.jpg
This is the final fix to the valley on the right side of the house. Added flashing material is being added. (30-Jun-04)dozer00000
(0 votes)