Top rated - DrDave's Gallery |
Cement MixerAll the concrete and mortar for the project was mixed onsite with this gas-powered mixer (provided by the builder).DrDave (0 votes)
|
|
Roof Structure & PanelsHere you can see the steel structure with the first of the panels installed.DrDave (0 votes)
|
|
Starting the Roof PanelsAlthough you can't see it in this picture, we used standard 50x150 composite panels, but had them cut in half (75cm length) to give them a better look (more like the smaller concrete roof tiles). Since the labor contract was fixed-price, our only extra cost in doing this was that we needed twice as many fastener hooks. No extra steel was required.DrDave (0 votes)
|
|
Day #1 - Foundation LayoutOn the first day of construction, the house footprint was located on the land from some rough markings my wife and I had placed before we returned to Phuket two days earlier. All of the land under the floor beams, as well as the holes for the column footings was hand-dug.DrDave (0 votes)
|
|
Column BasePouring the concrete for the first column footing.DrDave (0 votes)
|
|
Column BaseThe columns (sowpoons) are set in about 30cm of concrete.DrDave (0 votes)
|
|
Setting the Forms for the Ground BeamsDrDave (0 votes)
|
|
|
|
|
|
|