100_0202.JPG
Pouring the beams (2). Greater accuracy is achieved using the tube slung below the bucket. The flow is still controlled by the 'jockey'.Thaifu T00000
(1 votes)
100_0201.JPG
Pouring the beams (1). CPAC deliver the concrete and pour into the bucket; hoisted by crane; then the 'jockey' releases the concrete at the appropriate moment.Thaifu T00000
(1 votes)
100_0171.JPG
My first view on arriving from the UK. Concrete base laid; steel work for columns started; metal shuttering delivered. Note the 'good luck' artefacts hanging from the columns following the usual 'blessing' by the monksThaifu T00000
(1 votes)
100_0200.JPG
'Hotel California' Some of the workers lived here during the whole construction phase. Actually this helps with site security at night. Later the 'hotel' was doubled in size to accommodate more workers.Thaifu T00000
(1 votes)
100_0199.JPG
Doing the shuttering for the beams. Wish my football team had as much supportThaifu T00000
(1 votes)
100_0193.JPG
All columns finished, they are clad in 'cling film', I presume to assist the curing process. Now working on the steel work for the beamsThaifu T00000
(1 votes)
100_0179.JPG
Metal shuttering going up for columns. In the foreground, metal supports to be used for doing the beams.Thaifu T00000
(1 votes)
100_0183.JPG
Aligning the columns, getting ready for pouring concreteThaifu T00000
(1 votes)
100_0185.JPG
'Pouring' columns, CPAC deliver concrete; poured into tank. Then 'hand-balled' in small buckets to be poured from the top.Thaifu T00000
(1 votes)
     