Home > House Construction > Chok Dee #2 > Finishing

Top rated - Finishing
IMG_9425.jpg
Painting Door TrimThe door frame being painted. The sides are properly masked prior to painting. dozer00000
(0 votes)
IMG_9440.jpg
Wood Trim being AppliedWood trim being applied to the corner section of the tiered ceiling. Glue is applied to the underside of the trim prior to nailing in place via an air gun. dozer00000
(0 votes)
IMG_9441.jpg
Wall Tiles AppliedThe lower row of tiles is supported by concrete nails. This level is where the floor tiles will be after they are laid. Spacers are used to ensure consistent spacing. The surface is roughed prior to laying the tiles.dozer00000
(0 votes)
IMG_9445.jpg
Joint RepairThe joints are puttied to make so the wood looks as if it were one piece. The joints are miter cut to fit together at a 45 degree angle.dozer00000
(0 votes)
IMG_9449.jpg
PuttyThe fill putty is colored using the urethane as applied to the original wood trim to achieve a matching color. dozer00000
(0 votes)
IMG_9317.jpg
Painting the Patio CeilingThe patio ceiling is made of the water resistant drywall plasterboard. Here a primer coat is being applied. dozer00000
(0 votes)
IMG_9324.jpg
Bathroom Sink CounterPreparation for the pour of the bathroom sink. The same method is used as in the kitchen counter, the rebar used in the 6 mm thickness. The concrete will not be poured in the circular area where the sink will go and an open area will be left for the faucet. dozer00000
(0 votes)
IMG_9326.jpg
Counter after PourThe bathroom counter after the pour. The faucet will set off to the right side of the sink where the PVC pipe is. dozer00000
(0 votes)
IMG_9224.jpg
Shower EnclosureThe shower enclosure showing the blue glass blocks laid in place to be flush with the ceramic tile finish upon completion. dozer00000
(0 votes)
IMG_9237.jpg
Kitchen CounterRebar meshing in the counter is laid in a 10 centimeter square mesh. Concrete will be poured in the forms to make the counter. There will be a place holder for the sink and faucet (on the right). dozer00000
(0 votes)
IMG_9279.jpg
Stone TrimA close up of the red stone trim applied to the exterior patio columns. This is affixed with a adhesive cement product.dozer00000
(0 votes)
IMG_9293.jpg
Patio PourShows the pour of the patio area. The columns are protected during the pour as cement and other discolorants are hard to clean off the stone facing. dozer00000
(0 votes)