Most viewed - Cool Thai House Phase 2 |
Window Frame62 viewsA view of the window frame. There are two tracks, one for the screen and one for the window.dozer
|
|
Entry Room62 viewsThe entry room. Most of the house was tiled with super glossy granito tiles as in this room.dozer
|
|
Recessed Light61 viewsInstalling one recessed lighting fixture. dozer
|
|
Water Tank Electric Switch61 viewsAn electric solenoid floater type switch allows the switch to be configured to only turn on once the desired level as been reached. dozer
|
|
Concrete Hole Drill Bit61 viewsThe A/C guy had a nice drill bit to drill through concrete or aerated block. Much nicer than the hammer and chisel approach. dozer
|
|
A/C Mounting Plate61 viewsThe A/C mounting plate with the wires run by the original electrician. dozer
|
|
Water Tank61 viewsWould never buy this type of water tank again because the drain pipe is above ground leaving any residue trapped in the bottom of the tank (as opposed to stainless tanks which sit on a stand and drain directly through the lowest point at the bottom of the tank). dozer
|
|
Walkway61 viewsThere is a 1 m wide walkway along the front to the patio which goes all the way around the house. There is a step up to the patio of about 30 cm. dozer
|
|
Secured Storage61 viewsThe security partition to make a secured storage area. The partition is made of 1 by 1 lengths of metal welded into a mesh pattern.dozer
|
|
Still Digging Septics60 viewsThe septic chambers will each be about 2 meters deep and accommodate 6 round 1.2 m cement pieces. dozer
|
|
Inbound Water Test60 viewsDuring the inbound water pressure test the only place one should see any moisture is at the lids if they haven't be glued in place. dozer
|
|
PVC Pipe Lids60 viewsAll PVC piping is covered to prevent concrete or other blockage from getting in it. Also the covers allow the inbound lines to be pressure tested. dozer
|
|