DSC02283.JPG
50 viewsHere the foreman is doing the roof structure. The apex of the column is 4 meters (as can be seen imprinted on the top of the column) and is underground about 1 meter leaving about 3 meters. The stick is being used temporarily level the upper room beam. dozer
DSC02450.JPG
50 viewsWith this type of roofing the are two parallel c sections done on each ridge. Notice also the roofing is affixed to the metal by using a u bolt which penetrates the roof sheeting. dozer
20060911042.jpg
49 viewsSmall worker checks out the progress. dozer
DSC02374.JPG
49 viewsAttaching the grc synthetic corrugated roofing board to the roof structure. Brand of roofing was Elephant, thickness 5 mm. Notice the parallel metal c sections used to form the gutter in the roof valley. dozer
DSC02449.JPG
49 viewsGalvanized metal that comes in a roll 90cm wide is used to form the gutter. It is shaped so that it has a 10 cm wide gutter area which fits in the two parallel roof c sections. dozer
DSC02599.JPG
47 viewsAfter the exterior walls have been rendered. dozer
IMG_1770.JPG
47 viewsdozer
DSC02368.JPG
44 viewsThe 3" hard wood is hammered into place to create a surface for the fascia board to be attached. dozer
DSC02286.JPG
43 viewsThe roof apex is 1.5 m above the prefabricated columns. Here the foreman is setting the roof apex in place. dozer
DSC02269.JPG
Fill Dirt after Posts42 viewsThis build used 4 meter tall prefabricated columns. They were set in footings and allowed to dry for 1 week, then fill dirt was brought in to raise the floor level. dozer
DSC02274.JPG
Fill Brought In42 viewsShows the level of the dirt raised after fill is brought in via a tractor. The tractor was 500 per hour. dozer
IMG_8485.jpg
41 viewsThe upper ring beam partial pour. There are two pieces of 3 hun with the support being 2 hun. dozer