Most viewed - jazzman's Gallery |
Day 5593 viewsHad some unusual rain in Isaan for 2 days so the time was spent painting the rest of the steel in the shed, getting a truck load of dirt delivered, and bending more braces.
The ground beams are poured and the roof steel half finished. I still never fathomed out why they have to use a platform to load the mixer. Notice the plastic bags round my expensive steel scaffolding to protect it from cement (a lesson learned from previous jobs).jazzman
|
|
Day 8587 viewsMore progress on the walls. The 7 cm thick concrete floors have been laid in three of the rooms and the pits for the septic tanks have been dug. Wire mesh reinforcing was laid in the concrete.jazzman
|
|
Septic tanks581 viewsDouble-chamber septic tanks with leech system. Our substrate is hard clay and does not percolate to allow seepage tanks. The two in the picture serve two rooms; there will be an identical installation at the other end of the building for the other two rooms and the outside WC/shower and laundry room. Black water flows into the first tank which overflows into the second tank. Grey water goes directly into the second tank. There are no kitchens so a grease trap is not required.jazzman
|
|
Chasing580 viewsThe electricians started today chasing the walls for the electrical conduits. Although this is a low budget build, we're still using relatively good quality fittings, and concealed wiring. I've tried many times to teach the men to cut the channels with an angle grinder and just knock out the the stuff in the middle, but to no avail. Still using a hammer and a bent nail. Back home in France I have a special two-bladed power tool attachment for doing this.jazzman
|
|
Consumer Unit Large574 viewsConsumer Unit (pre equipped, modified by Jazzman), steel box, for 12 circuits, eg; Lighting, wall sockets, kitchen, 2 water heaters, 4 air con, garage/workshop, perimiter lighting and gate opener, swimming pool (goes to another sub consumer unit).
Can be surface or flush fitted.
Brand: Green
Equipment: 2-pole 60A master, minature RCBO with variable senitivity, various MCBs from 30A to 10A
Price: about 3,000 bahtjazzman
|
|
Cheap labour573 viewsFor all of those who are wondering why our labour bill of only 1,000 baht per square metre is so low...jazzman
|
|
day 4. Starting the roof steel573 viewsThe roof steel (ring-beam purlin) is bolted to the holes provided in the pre-formed cut-outs on the posts.jazzman
|
|
|
Ground beam 'formwork'559 viewsAs mentioned, this is a low budget Thai style construction. We will be pouring the ground-beam concrete directly into the trenches in the earth, when the trenches have been lined with plastic sheeting. This will also fill the rest of the footing holes to lock everything in place.
The ground beams a re 20 x 20 with four runs of RB9 and RB6 braces at 20 cm.jazzman
|
|
Day 2 Materials549 viewsOrganising the materials, painting the steel with red oxide, straightening the rebar and digging the first couple of holes.
The sand cost 280 baht/cu, the gravel 380 baht/cu, and the TPI cement 95 baht per 50 kg bag. The smooth 9 mm rebar (RB9) cost 38 baht per 10 m length.
The pre cast reinforced columns 15 x 15cmx 2.50 m columns cost 275 baht each. They come with a cut-out on the top with a hole for bolting a steel or wooden ring-beam.jazzman
|
|
548 viewsThis 9 cm thick breezeblock is for heavy duty use. It is made with high grade portland cement. It can be used for load bearing walls if rebar is used and the holes a re filled with concrete. They can also be used for building small swimming pools.
They cost 8 baht each.jazzman
|
|
Kitchen view 2539 viewsThe cooker hood was got cheap for 6,500 baht from Home Pro, Udon. Normal price was baht 13,000 but it was in a sale because it had been a demo on a display board in the shop. The two-ring glass cooker hob cost about 4,000 baht (if I remember rightly) from Global House, and the stainless steel double sink and drainer cost about 2,700 complete with tap (faucet), drains, and underneath plumbing pipes and U-bends.jazzman
|
|