29 Jan. 2009199 viewsSo here we are at the end of day on the 29th. Insect system installed and 10 columns poured along with the delivery of the floor panels. All in all a good week of progress on the Phala House. Stay tuned for more.pklongball
19 March 2009199 viewsA view from the back patio area looking into the kitchen door and office area window.pklongball
21 March 2009199 viewsThis is a view of some blue pipe installed today. The Aircon company staff installed the copper tubing, electrical and drain lines for the 3 AC units that will be installed later but we took advantage of the open walls to hide some of the piping.pklongball