2nd_fl_layout.jpg
2nd floor layout132 viewsFinal layout except using old measurements. Final house will be 40 cm wider.pskog
IM000698.jpg
Ceiling tiles132 viewssomdet
03180033.JPG
132 viewsCookieboy
03080001.JPG
132 viewsCookieboy
01092008485.jpg
tiling in the master ensuite132 viewskornoipaddy
5_Jan_Arrival9.JPG
Up she goes132 views5 Jan 09 One of the 2 columns going up during the ceremonypklongball
P5052157.JPG
5 May132 viewsHere we can see a more normal stepped ceiling in the smaller guest bedroom.pklongball
P5202263.JPG
20 May132 viewsThe ceiling "mud" man. The 2 bathrooms are the last to be finished.pklongball
IMG_4379.JPG
Measure land infill height132 viewsUsing a water tube, the height of the soil infill is measured. It should be 50 cm, but it was found to vary between 25 and 40 cm. Hence the soil man was told to fill to the agreed level of 50 cm, and not beat around the bush, by saying the land is uneven in places. Payment is being withheld until 50 cm is achieved on the whole land.

The agreement was verbal - next time everything will be in writing - lesson learnt - don't trust anyone.
Max&Bee-in-CM
129Carport.JPG
132 viewspklongball
IM000638.jpg
Master bathroom131 viewsTiles going up in the master bath. This has been a nightmare with them not having enough tiles, breaking whole boxes worth, putting tiles in the wrong place, etc. For some reason, this has been the biggest headache of the whole project so far (except for the wood floor).somdet
03030012.JPG
131 viewsCookieboy